F-00239 - Is a shorter contract term acceptable for the Accredited GreenPower/Off-Site Renewables criteria in Energy?
Yes, projects may use shorter contract terms to target the Accredited GreenPower®/Off-site Renewables criteria within the Greenhouse Gas Emissions credit or the Renewable Electricity and Renewable Energy criteria under the Energy Source credit, on the condition that the shortest contract length must either be: Three (3) years, or  One (1) year, where...
Published on Tue, 10 Dec 2024
F-00115 - Can off-site renewable energy (e.g. GreenPower) be apportioned over the length of the building power supply contract?
Yes. For projects targeting the Reference Building/Fitout Pathway, where the percentage of off-site renewable energy is procured in stages over the length of the supply contract, the effective percentage of the supply contract can be applied. This is done by multiplying the percentage of off-site supply by the percentage of the...
Published on Tue, 10 Dec 2024
F-00367 - When should project teams submit for the optional Designed Assessment / Design Review?
The GBCA has no specific requirement as to when registered projects should submit for a Designed Assessment. Below is some guidance to help establish the best timing for your project. This supplements information provided in the rating tool Submission Guidelines.  Purpose A Designed Assessment (or Design Review under the Legacy rating tools)...
Published on Wed, 24 Jan 2024
F-00335 - How can project teams demonstrate compliance when a contractor has become insolvent?
The GBCA recommends that, when a contractor, sub-contractor, consultant, or other party involved in a Green Star registered project is unable to complete project works or provide documentation for the Green Star submission due to insolvency or another unforeseen event, the project team should contact the GBCA as soon as...
Published on Tue, 1 Aug 2023
F-00286 - Instances where a technical question no longer needs to be submitted by a project team
Technical questions related to Innovation were previously marked as free of charge. However moving forward Innovation related technical questions will be charged the standard fees of $220 (excl. of GST) as per a technical question. The following is a list of all places in the rating tool where a technical...
Published on Mon, 17 Oct 2022
F-00238 - Is there an alternative pathway for projects to target Credit 15B.2.3 Domestic Hot Water?
Yes. Projects may target 2 points under 15B.2.3 Domestic Hot Water from Green Star - Design & As Built by using an electric heat pump with a minimum COP of 3.5 on the condition that the heat pump will be powered by 100% renewable energy (on-site or off-site).       
Published on Fri, 23 Sep 2022
F-00021 - Can Large-scale Generation Certificates (LGC's) be used in Green Star projects?
Yes, large-scale generation certificates (LGCs) are accepted in Green Star in the following scenarios; On Site Renewables Electricity from on-site systems where LGCs or STCs are generated. Off Site Renewables  Renewable electricity purchased directly from a generator / retailer through a PPA or contract where LGC’s are provided to user and the LGCs are...
Published on Wed, 18 Aug 2021
F-00200 - Can projects consider an all-electric reference case when pursuing a fully electric electric building under credit 15E?
Yes, buildings that are designed to be fully electric may use an all-electric reference case when targeting 15E Greenhouse gas emissions - Reference Building Pathway from Green Star - Design & As Built v1.2 and Green Star - Design & As Built v1.3. For projects located where the published grid carbon...
Published on Mon, 31 Jan 2022
F-00181 - How do I know what type of documentation is accepted for a Design Review rating?
We’ve developed a short guidance document for project teams on what level of documentation is acceptable for Design Review – Green Star Design & As Built and Green Star – Interiors. This Design Review Guidance provides answers to common questions asked by project teams. The Guidance - Submitting for Design Review document is...
Published on Fri, 13 Nov 2020
F-00178 - Can project teams use the Market-Based Method when targeting off-site renewables in the GHG credit?
Yes. Project teams using a Market-Based Method approach in line with the 'GHG Protocol Scope 2 Guidance' amendment of the GHG Protocol Corporate Standard to account for the purchase of 100% off-site renewable energy may claim 100% off-site renewables in the Greenhouse Gas Emissions credit in Green Star - Design &...
Published on Tue, 20 Oct 2020
F-00163 - How are Appliances and IT equipment without a MEPS rating treated for the purposes of the 'Energy Credit' in Green Star?
For the purposes of the 'Greenhouse Gas Emissions' credit in Green Star - Design & As-Built and Green Star - Interiors, where Appliances and IT equipment's used on the project, do not have a MEPS ratings, the project team may team use the alternative approach to demonstrate compliance with the...
Published on Fri, 25 Sep 2020
F-00161 - Can the project team use the latest emission factors for the purposes of the 'Greenhouse Gas Emissions' Credit?
Yes, project teams targeting the 'Greenhouse Gas Emission' credit using the Reference building/Fitout pathway can use updated Greenhouse Gas Emissions Factors within the Green Star - Design & As Built: Greenhouse Gas Emissions Calculator on the following conditions:   The updated emissions factors must be current at the time of either...
Published on Thu, 3 Sep 2020
F-00165 - At As Built, can I use the same energy modelling report that was submitted and awarded at Design Review?
Yes, conditionally.  At As Built, the same energy modelling report may be submitted for 15E Reference Building Pathway, if it was submitted and awarded at Design Review and no changes have been made to the design, on the following conditions:  The energy modelling report is to be accompanied by a confirmation letter...
Published on Fri, 3 Jul 2020
F-00156 - Can a Class 2 building use a just-compliant NatHERs building envelope load rather than Class 3 modelling?
Class 2 multi-unit residential projects may use a Class 2 NCC just-compliant NatHERs building fabric/envelope load as the reference case for the purposes of credit 15E - Greenhouse Gas Emissions Reduction - Reference Building Pathway. The project team may scale (increase) the annual hourly heating and cooling loads obtained from...
Published on Fri, 19 Jun 2020
F-00131 - Can projects targeting the NatHERS pathway claim points for Peak Electricity Demand Reduction?
Yes. Projects targeting the NatHERS pathway may target one (1) point under credit 16B 'Modelled Performance Pathway: Reference Building' by demonstrating that the building has an average NatHERS rating of 7.5 stars, and no individual dwelling has a rating of less than 7 stars.    An average NatHERS rating of 7.5 stars...
Published on Fri, 8 May 2020
F-00095 - Can I use 'For Construction' drawings in the As Built submission?
Yes. The GBCA requires evidence that the drawings supplied are as constructed, whether they have an ‘As Built’ stamp or not. 'For Construction' drawings are acceptable provided they are accompanied by formal confirmation from the head contractor or other relevant professional(s) that the For Construction drawings depict the site as-built...
Published on Tue, 31 Mar 2020
F-00122 - Can I promote my project if it is registered for Green Star, but not yet certified?
Before achieving certification you can promote your Green Star registered project in writing, but cannot use the Green Star logo or Green Star certification trade mark. The Green Star certification trade mark can only be used once the project is certified. The Marketing and Style Guide explains how Green Star certified projects can...
Published on Mon, 6 Jan 2020
F-00006 - Is the supporting documentation listed in each credit required for submission?
No. All supported documentation listed for each credit in the Submission Guidelines are suggestions only, unless specified otherwise. Alternate documentation to those listed can be used by project teams to demonstrate credit compliance if it adequately supports the claims made within the Submission Templates.
Published on Tue, 26 Jun 2018
F-00026 - Submission formatting: referencing files in multiple credits
Documents can be referenced, rather than duplicated in credits, as long as the Submission Templates include both: hyperlinks to the relevant document(s); and references to specific page numbers within the document(s) which demonstrate compliance with the specific credit. Page numbers are likely to change for each credit submission, as appropriate to the credit compliance being demonstrated. Please note...
Published on Mon, 16 Jul 2018
F-00109 - Can Green Star be used on a project outside of Australia?
The Green Building Council of Australia (GBCA) does not normally certify Green Star projects outside of Australia. If you believe your project should be considered as an exception circumstance, please complete an Eligibility query and provide details of your project and why this should be considered for Green Star certification. Alternatively, we...
Published on Tue, 6 Aug 2019

Disclaimer

These FAQs are:

  • provided as additional technical assistance for Green Star users.
  • optional and free to use on Green Star projects.

When used on Green Star projects, make sure to:
  • state the FAQ number on the Submission Template.
  • click on "Download" to save the FAQ.
  • include the PDF in the submission.